- The installation and connection of HDPE plastic in the new production ponds A1, A4, A5, and B7 have been completed. Tomorrow, the next tasks will begin with the installation of pipes, diffusers, and the construction of the Anco bridge. Early next week, water will start to be added for the processing stage.
2. The warehouse construction is ongoing, and tomorrow the walls will start to be built, with containers being moved. The construction is expected to be completed by July 20th.
3. The stocking in ponds B3, B4, and B5 is progressing smoothly according to plan. The PLB seeds are healthy, active, and virus-free. The bioassay results show that the seeds survive without oxygen for 3×24 hours.
4. The PCR test results for ponds A3, A6, and A7 are not perfect yet, as pond A6 is infected with the IMNV virus. Treatment has been carried out, and the results are expected to be negative tomorrow, with the seeds ready for stocking in the coming days.
On July 10th, there will be an inspection visit from the BKPM Jakarta office to the PT SMM shrimp farm, and the necessary data has been prepared as part of the preparations.